01 / Case studies
From field constraints
to coordinated action.
Four examples of delivery, recovery, safety follow-through, and project controls.
01 / Refinery delivery
Completed scopeFive concurrent scopes.
Zero rework.
25%shorter duration
U-type / floating-head group
I coordinated defined exchanger-maintenance scope through inspection, acceptance, and return to service at YASREF.
Team delivery outcome · four weeks planned, three weeks actual for this equipment group.
Read the YASREF delivery case ↗
02 / Schedule recovery
In progressRebuilding execution
after a contractor withdrawal.
DailyKPI and constraint review
against the recovery plan
I supported the contractor transition, rebuilt execution priorities, and coordinated resources and field handover around critical activities.
Active tank T&I · final handover and return to service remain pending.
Read the recovery approach ↗
03 / Field HSE
Recorded set closed18 findings.
Followed through to closure.
18 / 18recorded findings closed
within 48 hours
14 Same shift4 Follow-up within 48h
I raised unsafe conditions with contractor supervision and followed agreed corrective actions through field correction.
Current-assignment findings only · 78% corrected in the same shift.
Read the HSE intervention ↗
04 / Project controls
Weekly reviewFragmented records.
One connected view.
SES / RPOstatus, line items, and balances
connected for management review
I built and maintained an Advanced Excel tracker using planner inputs and source records to improve execution and commercial visibility.
SAP remained the enterprise source of record.
Read the controls case ↗